The North Blyth Biomass Power Station Order 2013

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

  1. Introductory Text

  2. 1.Citation and commencement

  3. 2.Interpretation

  4. 3.Development consent etc granted by the Order

  5. 4.Procedure in relation to approvals etc under the Requirements

  6. 5.Maintenance of authorised development

  7. 6.Operation of generating station

  8. 7.Benefit of Order

  9. 8.Defence to proceedings in respect of statutory nuisance

  10. 9.Street works

  11. 10.Agreements with street authorities

  12. 11.Discharge of water

  13. 12.Authority to survey and investigate the land

  14. 13.Compulsory acquisition of land

  15. 14.Compulsory acquisition of land – incorporation of the minerals code

  16. 15.Time limit for exercise of authority to acquire land compulsorily

  17. 16.Compulsory acquisition of rights

  18. 17.Private rights of way

  19. 18.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

  20. 19.Acquisition of subsoil only

  21. 20.Acquisition of part of certain properties

  22. 21.Rights under or over streets

  23. 22.Statutory undertakers

  24. 23.Recovery of costs of new connections

  25. 24.Railway and navigation undertakings

  26. 25.Application of landlord and tenant law

  27. 26.Operational land for purposes of the 1990 Act

  28. 27.Deemed licence for purposes of the 2009 Act

  29. 28.Certification of plans etc

  30. 29.Arbitration

  31. 30.Crown rights

  32. 31.Protective provisions

  33. Signature

    1. SCHEDULE 1

      Authorised development

      1. 1.In Northumberland the construction use and maintenance of a nationally...

      2. 2.Associated development within the meaning of section 115(2) of the...

    2. SCHEDULE 2

      Requirements

      1. 1.Interpretation

      2. 2.Time limits

      3. 3.Detailed design

      4. 4.Highway accesses

      5. 5.Fencing and other means of enclosure

      6. 6.Surface and foul water drainage

      7. 7.Surface water drainage – contamination

      8. 8.Contaminated land and groundwater

      9. 9.Disposal of contaminated materials

      10. 10.Earthworks and remediation

      11. 11.Ecological management

      12. 12.Code of construction practice and CEMP

      13. 13.Suppression of dust and dirt during construction

      14. 14.Construction traffic routing and management plan

      15. 15.Control of noise during construction and commissioning

      16. 16.External lighting during construction

      17. 17.Unexploded ordnance (UXO) survey

      18. 18.Travel plan – construction

      19. 19.Flooding – mitigation

      20. 20.Flooding – warning and evacuation plan

      21. 21.Fire prevention

      22. 22.Otter mitigation strategy

      23. 23.Asbestos

      24. 24.Storage of liquids on site

      25. 25.Database of tall structures

      26. 26.Aviation safety

      27. 27.European protected species

      28. 28.Construction hours

      29. 29.Piling and vibration

      30. 30.Control of artificial light emissions

      31. 31.Control of dust emissions

      32. 32.Waste management on site

      33. 33.Travel plan and traffic management plan – operational period

      34. 34.Combined heat and power

      35. 35.Site safety and signage

      36. 36.Control of noise during operational phase

      37. 37.External storage

      38. 38.Deliveries of fuel stock by road

      39. 39.Biomass fuel sustainability

      40. 40.Decommissioning

      41. 41.Workforce development strategy

      42. 42.Requirement for written approval

      43. 43.Amendments to approved details

    3. SCHEDULE 3

      Streets subject to street works

    4. SCHEDULE 4

      Deemed licence under the Marine and Coastal Access Act 2009

      1. PART 1 Licensed marine activities

        1. 1.Interpretation

        2. 2.Details of licensed activities

      2. PART 2 Conditions applying to licensed activities

        1. General conditions

          1. 1.Notification of commencement and completion

          2. 2.Project wide conditions

          3. 3.Activity specific conditions

    5. SCHEDULE 5

      Protective provisions

      1. 1.For the protection of Network Rail

      2. 2.In this Schedule— “construction” includes execution, placing, alteration and reconstruction...

      3. 3.(1) Where, under this Schedule, Network Rail is required to...

      4. 4.(1) The undertaker shall not exercise the powers conferred by...

      5. 5.(1) The undertaker shall before commencing construction of any specified...

      6. 6.(1) Any specified work and any protective works to be...

      7. 7.The undertaker shall— (a) at all times afford reasonable facilities...

      8. 8.Network Rail shall at all times afford reasonable facilities to...

      9. 9.(1) If any permanent or temporary alterations or additions to...

      10. 10.The undertaker shall repay to Network Rail all reasonable fees,...

      11. 11.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

      12. 12.If at any time after the completion of a specified...

      13. 13.The undertaker shall not provide any illumination or illuminated sign...

      14. 14.Any additional expenses which Network Rail may reasonably incur in...

      15. 15.(1) The undertaker shall pay to Network Rail all reasonable...

      16. 16.Network Rail shall, on receipt of a request from the...

      17. 17.In the assessment of any sums payable to Network Rail...

      18. 18.The undertaker and Network Rail may, subject in the case...

      19. 19.Nothing in this Order, or in any enactment incorporated with...

      20. 20.The undertaker shall give written notice to Network Rail if...

      21. 21.The undertaker shall no later than 28 days from the...

  34. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources