Search Legislation

The Longfield Solar Farm Order 2023

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 18

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The Longfield Solar Farm Order 2023, Section 18. Help about Changes to Legislation

Compulsory acquisition of landE+W+S

18.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development, or to facilitate it, or as is incidental to it.

(2) This article is subject to article 19 (time limit for exercise of authority to acquire land compulsorily), article 20(2) (compulsory acquisition of rights), [F1article 23] (acquisition of subsoil only), [F1article 26] (rights under or over streets), article 27 (temporary use of land for constructing the authorised development) and schedule 15 (protective provisions).

Textual Amendments

Commencement Information

I1Art. 18 in force at 18.7.2023, see art. 1