- Latest available (Revised)
- Original (As made)
There are currently no known outstanding effects for the The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
23.Compulsory acquisition of land – incorporation of the mineral code
24.Time limit for exercise of authority to acquire land and rights compulsorily
27.Extinguishment of private rights and restrictive covenants relating to apparatus removed from land subject to temporary possession
39.Temporary use of land for maintaining the authorised development
PART 6 MISCELLANEOUS AND GENERAL
SCHEDULES
STREETS, CYCLE TRACKS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
2.(1) Without limitation on the scope of paragraph 1, the...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
LAND IN WHICH ONLY NEW RIGHTS AND RESTRICTIVE COVENANTS ETC. MAY BE ACQUIRED
PART 1 PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
PART 2 PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 4 FOR THE PROTECTION OF RAILWAY INTERESTS
26.The provisions of this Part of this Schedule have effect,...
27.In this Part of this Schedule— “asset protection agreement” means...
28.(1) Where under this Part of this Schedule Network Rail...
29.(1) Subject to sub-paragraph (2) the undertaker must not exercise...
30.(1) The undertaker must before commencing construction of any specified...
32.The undertaker must— (a) at all times afford reasonable facilities...
33.Network Rail must at all times afford reasonable facilities to...
34.(1) If any permanent or temporary alterations or additions to...
35.The undertaker must repay to Network Rail all reasonable fees,...
36.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
38.The undertaker must not provide any illumination or illuminated sign...
39.Any additional expenses which Network Rail may reasonably incur in...
40.(1) The undertaker must pay to Network Rail all reasonable...
43.The undertaker and Network Rail may, subject in the case...
44.Nothing in this Order, or in any enactment incorporated with...
45.The undertaker must give written notice to Network Rail if...
PART 5 FOR THE PROTECTION OF NORTHERN POWERGRID
47.For the protection of Northern Powergrid the following provisions have...
49.This Part of this Schedule does not apply to apparatus...
50.Regardless of any provision in this Order or anything shown...
52.(1) Where, in accordance with the provisions of this Part...
53.(1) Not less than 48 days before starting the execution...
54.(1) Subject to the following provisions of this paragraph, the...
55.(1) Subject to sub-paragraphs (2) and (3), if by reason...
56.Nothing in this Part of this Schedule affects the provisions...
57.Where in consequence of the proposed construction of any of...
58.If in consequence of an agreement reached in accordance with...
59.The plans submitted to Northern Powergrid by the undertaker pursuant...
60.Where practicable, the undertaker and Northern Powergrid will make reasonable...
PART 7 FOR THE PROTECTION OF NATIONAL GAS TRANSMISSION PLC AS GAS UNDERTAKER
PART 8 FOR THE PROTECTION OF NORTHERN GAS NETWORK’S APPARATUS
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: