Compulsory Purchase (Vesting Declarations) Act 1981, SCHEDULE A1 is up to date with all changes known to be in force on or before 29 December 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
Section 12
Textual Amendments
F1Sch. A1 inserted (3.2.2017) by Housing and Planning Act 2016 (c. 22), s. 216(3), Sch. 18 para. 6; S.I. 2017/75, reg. 3(k) (with reg. 5)
Modifications etc. (not altering text)
C1Sch. A1 excluded by 2017 c. 7, s. 7(2) (as amended) (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 2; S.I. 2017/209, reg. 2
C2Sch. A1 excluded by 2017 c. 7, s. 8(2) (as amended) (24.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(2), Sch. 14 para. 3; S.I. 2017/209, reg. 2
C3Sch. A1 excluded (19.12.2017) by The Network Rail (Buxton Sidings Extension) Order 2017 (S.I. 2017/1150), arts. 1, 22(3) (with arts. 22(4), 32(2))
C4Sch. A1 excluded (22.12.2017) by The M20 Junction 10a Development Consent Order 2017 (S.I. 2017/1202), arts. 1, 29(3)(b) (with arts. 4, 29(4), 37)
C5Sch. A1 excluded (4.1.2018) by The Blackpool Tramway (Blackpool North Extension) Order 2017 (S.I. 2017/1214), arts. 1, 30(3)(b) (with arts. 30(4), 58, 59)
C6Sch. A1 excluded (18.4.2018) by The Network Rail (Hope Valley Capacity) Order 2018 (S.I. 2018/446), arts. 1, 21(4)(b) (with arts. 24(8), 33(2))
C7Sch. A1 excluded (31.5.2018) by The Silvertown Tunnel Order 2018 (S.I. 2018/574), arts. 1(2), 27(4)(b) (with art. 27(5))
C8Sch. A1 excluded (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 22(3)(b) (with arts. 22(4), 31(2))
C9Sch. A1 excluded (3.10.2018) by The A19/A184 Testos Junction Alteration Development Consent Order 2018 (S.I. 2018/994), arts. 1, 27 (with arts. 3(3), 5)
C10Sch. A1 excluded (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 26(3)(b)(4) (with arts. 55, 56)
C11Sch. A1 excluded (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 24(3)(b) (with art. 24(4))
C12Sch. A1 excluded (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 25(3)(b) (with art. 25(4))
C13Sch. A1 excluded (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 25(3)(b) (with art. 25(4))
C14Sch. A1 excluded (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1(1), 31(3)(b) (with arts. 3(1), 31(4))
C15Sch. A1 excluded (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 23(3)(b) (with arts. 7, 23(4))
C16Sch. A1 excluded (30.4.2020) by The A585 Windy Harbour to Skippool Highway Development Consent Order 2020 (S.I. 2020/402), arts. 1, 27(3)(b) (with arts. 5, 27(4), 44)
C17Sch. A1 excluded (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 25(3)(b) (with arts. 7, 25(4))
C18Sch. A1 excluded (21.5.2020) by The Lake Lothing (Lowestoft) Third Crossing Order 2020 (S.I. 2020/474), arts. 1, 27(4)(b) (with arts. 51, 57)
C19Sch. A1 excluded (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 31(3)(b) (with arts. 31(4), 37)
C20Sch. A1 excluded (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 27(3)(b) (with arts. 5, 27(4), 44)
C21Sch. A1 excluded (19.6.2020) by The Cleve Hill Solar Park Order 2020 (S.I. 2020/547), arts. 1, 21(3)(b) (with arts. 21(4), 37)
C22Sch. A1 excluded (6.8.2020) by The A19 Downhill Lane Junction Development Consent Order 2020 (S.I. 2020/746), arts. 1, 27(3)(b) (with arts. 5, 27(4))
C23Sch. A1 excluded (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 24(3)(b) (with art. 24(4), Sch. 9 para. 144)
C24Sch. A1 excluded (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 33(4)(b) (with art. 33(5))
C25Sch. A1 excluded (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 28(3)(b) (with arts. 28(4), 32, Sch. 9 para. 36)
C26Sch. A1 excluded (22.1.2021) by The Hornsea Three Offshore Wind Farm Order 2020 (S.I. 2020/1656), arts. 1, 23(3) (with arts. 23(4), 40, 41, Sch. 9 Pt. 5 para. 18)
C27Sch. A1 excluded (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 30(3)(b) (with arts. 5, 30(4), Sch. 27 para. 36)
C28Sch. A1 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), ss. 7(2)(b), 64(1) (with s. 7(3))
C29Sch. A1 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), ss. 6(2)(b), 64(1)
C30Sch. A1 excluded (19.2.2021) by The A303 Sparkford to Ilchester Dualling Development Consent Order 2021 (S.I. 2021/125), arts. 1, 31(3)(b) (with arts. 4, 31(4), 47)
C31Sch. A1 excluded (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 26(3)(b) (with arts. 15, 50, Sch. 11 para. 29)
C32Sch. A1 excluded (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), arts. 1, 24(3)(b) (with arts. 41, 42, Sch. 17 para. 66)
C33Sch. A1 excluded (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), arts. 1, 24(3)(b) (with arts. 24(4), 41, 42, Sch. 16)
C34Sch. A1 excluded (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 25(b) (with Sch. 8 Pt. 6 para. 19)
C35Sch. A1 excluded (25.3.2022) by The Bridgwater Tidal Barrier Order 2022 (S.I. 2022/299), arts. 1, 35 (with art. 55)
C36Sch. A1 excluded (22.4.2022) by The East Anglia ONE North Offshore Wind Farm Order 2022 (S.I. 2022/432), arts. 1(2), 24(3)(b) (with arts. 40, 41)
C37Sch. A1 excluded (22.4.2022) by The East Anglia TWO Offshore Wind Farm Order 2022 (S.I. 2022/433), arts. 1(2), 24(3)(b) (with arts. 24(4), 40, 41)
C38Sch. A1 excluded (12.5.2022) by The M54 to M6 Link Road Development Consent Order 2022 (S.I. 2022/475), arts. 1, 27(3)(b) (with art. 27(4))
C39Sch. A1 excluded (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 30(3)(b) (with arts. 6, 30(4), 34)
C40Sch. A1 excluded (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 32(3)(b) (with arts. 5, 32(4), 36)
C41Sch. A1 excluded (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 32(3)(b) (with arts. 4, 32(4), 50)
C42Sch. A1 excluded (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 35 (with arts. 35(4), 62, 76, 87)
1(1)This Schedule applies where an acquiring authority have executed a general vesting declaration in respect of part only of a house, building or factory.E+W
(2)But see section 2A of the Acquisition of Land Act 1981 (under which a compulsory purchase order can exclude from this Schedule land that is 9 metres or more below the surface).
2E+WA person able to sell the whole of the house, building or factory (“the owner”) may serve a counter-notice requiring the authority to purchase the owner's interest in the whole.
3E+WA counter-notice under paragraph 2 must be served before the end of the period of 28 days beginning with the day the owner first had knowledge of the general vesting declaration.
4E+WIn a case where this Schedule applies by virtue of a general vesting declaration executed after a counter-notice has been served under paragraph 4 or 17 of Schedule 2A to the Compulsory Purchase Act 1965, that counter-notice is to have effect as a counter-notice served under this Schedule.
5E+WIn this Schedule—
“additional land” means the part of the house, building or factory not specified in the general vesting declaration;
“house” includes any park or garden belonging to a house;
“land proposed to be acquired” means the part of the house, building or factory specified in the general vesting declaration;
“notice to treat” means a notice to treat deemed to have been served under section 7(1);
“original vesting date” is the first day after the end of the period specified in the general vesting declaration in accordance with section 4(1).
6(1)On receiving a counter-notice the acquiring authority must decide whether to—E+W
(a)withdraw the notice to treat in relation to the land proposed to be acquired,
(b)accept the counter-notice, or
(c)refer the counter-notice to the Upper Tribunal.
(2)But the acquiring authority may not decide to withdraw the notice to treat if the counter-notice was served on or after the original vesting date.
7E+WThe authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”).
8E+WIf the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period.
9(1)This paragraph applies if the acquiring authority do not serve notice of a decision within the decision period.E+W
(2)If the counter-notice was served before the original vesting date, the authority are to be treated as if they had served notice of a decision to withdraw the notice to treat in relation to the land proposed to be acquired.
(3)If the counter-notice was served on or after the original vesting date, they are to be treated as if they had served notice of a decision to accept it.
10E+WIf the acquiring authority serve notice of a decision to withdraw the notice to treat in relation to the land proposed to be acquired the general vesting declaration is to have effect as if it did not include that land.
11(1)This paragraph applies where the acquiring authority serve notice of a decision to accept the counter-notice.E+W
(2)The general vesting declaration and the notice to treat (and, where applicable, the compulsory purchase order) are to have effect as if they included the owner's interest in the additional land as well as in the land proposed to be acquired.
(3)The authority must serve on the owner a notice specifying the vesting date or dates for—
(a)the land proposed to be acquired (if the counter-notice was served before the original vesting date), and
(b)the additional land.
(4)The new vesting date for the land proposed to be acquired must not be before the original vesting date.
(5)The vesting date for the additional land must be after the period of 3 months beginning with the day on which the notice under sub-paragraph (3) is served.
12(1)This paragraph applies where—E+W
(a)the acquiring authority refer the counter-notice to the Upper Tribunal, and
(b)the counter-notice was served before the original vesting date.
(2)At any time before the Upper Tribunal make a determination under paragraph 14, the acquiring authority may serve notice on the owner specifying a new vesting date for the land proposed to be acquired.
(3)The new vesting date for the land proposed to be acquired must not be before the original vesting date.
13E+WThis Part applies where, in accordance with paragraph 8, the acquiring authority refer a counter-notice to the Upper Tribunal.
14(1)The Upper Tribunal must determine whether the severance of the land proposed to be acquired would—E+W
(a)in the case of a house, building or factory, cause material detriment to the house, building or factory, or
(b)in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs.
(2)In making its determination, the Upper Tribunal must take into account—
(a)the effect of the severance,
(b)the proposed use of the land proposed to be acquired, and
(c)if that land is proposed to be acquired for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land.
15E+WIf the Upper Tribunal determines that the severance of the land proposed to be acquired would have either of the consequences described in paragraph 14(1) it must determine how much of the additional land the acquiring authority ought to be required to take in addition to the land proposed to be acquired.
16(1)This paragraph applies where the Upper Tribunal specifies in its determination that the acquiring authority ought to be required to take the whole or part of the additional land (“the specified land”).E+W
(2)The general vesting declaration and any notice to treat (and, where applicable, the compulsory purchase order) are to have effect as if they included the owner's interest in the specified land.
(3)The Upper Tribunal must order a vesting date for—
(a)the specified land, and
(b)any land proposed to be acquired which has not vested in the authority and for which no vesting date has been specified under paragraph 12.
[F2(4)If the vesting date for the specified land is after the vesting date for any land proposed to be acquired, the Upper Tribunal's power to award compensation under section 7 of the Compulsory Purchase Act 1965 includes power to award compensation for any loss suffered by the owner by reason of the temporary severance of the land proposed to be acquired from the specified land.]
Textual Amendments
F2Sch. A1 para. 16(4) inserted (19.7.2017) by Neighbourhood Planning Act 2017 (c. 20), ss. 41, 46(1); S.I. 2017/767, reg. 2(j)
17(1)This paragraph applies where—E+W
(a)the Upper Tribunal has specified in its determination that the acquiring authority ought to be required to take the whole or part of the additional land (“the specified land”), and
(b)the vesting date in relation to the land proposed to be acquired has not passed, and
(c)the vesting date in relation to the specified land has not passed.
(2)The acquiring authority may, within the period of 6 weeks beginning with the day on which the Upper Tribunal made its determination, withdraw the notice to treat in relation to the land proposed to be acquired together with the specified land.
(3)If the acquiring authority withdraws the notice to treat, the general vesting declaration is to have effect as if it did not include that land.
(4)If the acquiring authority withdraws the notice to treat under this paragraph they must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawal of the notice.
(5)Any dispute as to the compensation is to be determined by the Upper Tribunal.]
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: