PART 5 POWERS OF ACQUISITION AND POSSESSION OF LAND
29.Compulsory acquisition of land – incorporation of the mineral code
30.Statutory authority to override easements and other rights
31.Time limit for exercise of authority to acquire land compulsorily
32.Compulsory acquisition of rights and imposition of restrictive covenants
39.Temporary use of land for carrying out authorised development
40.Time limit for exercise of authority to temporarily use land for carrying out the authorised development
41.Temporary use of land for maintaining authorised development
43.Apparatus and rights of statutory undertakers in stopped-up streets
Deemed approval of requirements relating to Sizewell B relocated facilities permission 1 and 2
Streets to be permanently stopped up, changed in status or private means of access extinguished
Benefit of permanent private means of access and private rights of way created
Streets and private means of access to be temporarily closed
2.(1) Without limiting the scope of sub-paragraph (1), the Land...
3.(1) Without limiting the scope of sub-paragraph (1), the 1961...
6.The following provisions of the 1965 Act (which state the...
9.Section 22 of the 1965 Act (Interests omitted from purchase)...
10.For Schedule 2A of the 1965 Act substitute— SCHEDULE 2A...
Acquisition of wayleaves, easements and other rights
PART 1 PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
PART 2 PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS NETWORKS
19.The provisions of this Part of this Schedule have effect,...
20.In this Part of this Schedule— “construction” includes execution, placing,...
21.(1) Where under this Part of this Schedule Network Rail...
22.(1) The undertaker must not exercise the powers conferred by—...
23.(1) The undertaker must before commencing construction of any specified...
25.The undertaker must— (a) at all times afford reasonable facilities...
26.Network Rail must at all times afford reasonable facilities to...
27.(1) If any permanent or temporary alterations or additions to...
28.The undertaker must repay to Network Rail all reasonable fees,...
29.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
31.The undertaker must not provide any illumination or illuminated sign...
32.Any additional expenses which Network Rail may reasonably incur in...
33.(1) The undertaker must pay to Network Rail all reasonable...
36.The undertaker and Network Rail may, subject in the case...
37.Nothing in this Order, or in any enactment incorporated with...
38.The undertaker must give written notice to Network Rail if...
PART 5 FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKERS
PART 6 FOR THE PROTECTION OF ESSEX AND SUFFOLK WATER
58.For the protection of Essex and Suffolk Water, the following...
59.In this Part of this Schedule— “Authority” has the meaning...
60.The undertaker must not interfere with, build over or near...
61.The alteration, extension, removal or re-location of any apparatus shall...
62.In the situation, where in exercise of the powers conferred...
63.Regardless of any provision in this Order or anything shown...
64.If in consequence of the exercise of the powers conferred...
65.If in consequence of the exercise of the powers conferred...
66.If for any reason or in consequence of the construction...
67.Any agreement or approval of ESW required under these provisions...
68.Any dispute arising between the undertaker and ESW under this...
72.Following satisfaction of paragraph 71, ESW, acting reasonably, has confirmed...
74.Following satisfaction of paragraph 73, the Secretary of State for...
75.Following satisfaction of paragraph 74, the Authority has approved the...
PART 7 FOR THE PROTECTION OF EDF ENERGY NUCLEAR GENERATION LIMITED
PART 8 FOR THE PROTECTION OF THE NUCLEAR DECOMMISSIONING AUTHORITY AND MAGNOX LIMITED
Deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009
10.Local mariners, fishermen’s organisations and the UK Hydrographic Office must...
11.(1) The undertaker must provide the name, address and function...
13.The undertaker must ensure that a copy of this licence...
14.(1) No licenced activity may commence until a CPMMP (marine)...
15.(1) No licensed activity or phase of licensed activity must...
16.(1) No licensed activity or phase of licensed activity must...
17.(1) No licensed activity must commence until a FLCP has...
19.The storage, handling, transport and use of fuels, lubricants, chemicals...
21.Except for activities taking place below MHWS, concrete and cement...
22.If concrete is to be sprayed, suitable protective sheeting must...
23.During licensed activities, all wastes must be stored in designated...
24.The undertaker must ensure that any equipment, temporary structures, waste...
26.The undertaker must ensure that any vessels used for rock...
27.The undertaker must ensure that sea going tugs or tugs...
28.(1) No vessel movements within the Outer Thames Estuary Special...
29.(1) The undertaker must report all dropped objects to the...
31.(1) Cooling water abstraction must not commence until a MAP...
33.(1) No dredging activity or phase of dredging activity must...
36.Beach Landing Facility and Temporary Marine Bulk Import Facility
39.Cooling Water Intake and Outfall Heads, Shafts and Tunnels
44.(1) Water abstraction must not commence until a FIEMP has...
45.(1) Water abstraction must not commence until a SMP has...
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: