4.Maintenance, decommissioning and demolition of authorised development
19.Time limit for exercise of authority to acquire land compulsorily
21.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
25.Temporary use of land for carrying out the authorised development
26.Temporary use of land for maintaining authorised development
5.(1) The authorised development shall be carried out in accordance...
18.No part of the authorised development shall be carried out...
19.(1) Prior to commencement of construction Work No. 1 or...
21.(1) No part of the authorised development shall be brought...
22.In any case where the noise levels specified in requirement...
23.(1) Operation of the authorised development shall not be commenced...
35.(1) No part of the authorised development comprised in Works...
37.(1) The undertaker shall make a report (“monitoring report”) to...
38.(1) The generating station comprised in Work No. 1 shall...
51.Control of construction noise at North Killingholme Haven Pits
5.The licence holder must ensure that the MMO District Marine...
6.With respect to any conditions of this licence which require...
12.The licence holder must ensure that any coatings and treatments...
14.The licence holder must ensure that during the works all...
15.The licence holder must ensure that any equipment, temporary structures,...
16.(1) The licence holder must ensure that no waste concrete...
18.The licence holder must ensure that a Notice to Mariners...
21.No percussive piling shall take place between 7 April and...
22.Where piling is required to be undertaken during March, September...
23.No percussive piling shall take place before 0600 hours or...
PART 2 For the protection of the Environment Agency
1.(1) The following provisions shall apply for the protection of...
2.(1) Before beginning to construct any specified work, the undertaker...
3.Without prejudice to the generality of paragraph 2 but subject...
4.(1) Subject to sub-paragraph (2), any specified work, and all...
5.(1) Subject to sub-paragraph (6) the undertaker shall, from the...
6.Subject to paragraph 8, if by reason of the construction...
8.The undertaker shall indemnify the Agency in respect of all...
9.(1) Without prejudice to the other provisions of this Part...
PART 3 For the protection of Network Rail
1.The following provisions of this Schedule shall have effect unless...
2.In this Schedule— “construction” includes execution, placing, alteration and reconstruction...
3.(1) Where under this Schedule Network Rail is required to...
4.(1) The undertaker shall not exercise the powers conferred by...
5.(1) The undertaker shall before commencing construction of any specified...
7.The undertaker shall— (a) at all times afford reasonable facilities...
8.Network Rail shall at all times afford reasonable facilities to...
9.(1) If any permanent or temporary alterations or additions to...
10.(1) The undertaker shall repay to Network Rail all fees,...
12.Any additional expenses which Network Rail may reasonably and properly...
13.The undertaker shall not provide any illumination or illuminated sign...
14.(1) The undertaker shall pay to Network Rail all costs,...
16.The undertaker and Network Rail may, subject in the case...
17.Nothing in the Order, or in any enactment incorporated with...
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: