Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
PART 5 POWERS OF ACQUISITION AND POSSESSION
23.Compulsory acquisition of land – incorporation of the mineral code
24.Time limit for exercise of authority to acquire land compulsorily
25.Compulsory acquisition of rights and restrictive covenants
31.Temporary use of land for carrying out the authorised development
32.Temporary use of land for maintaining the authorised development
34.Apparatus and rights of statutory undertakers in stopped up streets
SCHEDULES
PERMANENT STOPPING UP AND ALTERATION OF HIGHWAYS, STREETS AND PRIVATE MEANS OF ACCESS
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWAGE UNDERTAKERS
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 3 FOR THE PROTECTION OF DRAINAGE AUTHORITIES
18.The provisions of this Part have effect for the protection...
19.In this Part of this Schedule— “construction” includes execution, placing,...
20.(1) Not less than 2 months before commencing construction of...
21.Without limiting the scope of paragraph 20, the requirements which...
22.(1) Subject to sub-paragraph (2), any specified work, and all...
23.(1) Subject to sub-paragraph (5), the undertaker must from the...
25.The undertaker must indemnify the drainage authority in respect of...
26.(1) Without limiting the other provisions of this Part of...
28.Any dispute arising between the undertaker and the drainage authority...
PART 4 FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY UNDERTAKER
PART 5 FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: