- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Pwynt Penodol mewn Amser (10/03/2023)
- Gwreiddiol (Fel y'i Deddfwyd)
Version Superseded: 18/07/2023
Point in time view as at 10/03/2023. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
New Roads and Street Works Act 1991, Section 85 is up to date with all changes known to be in force on or before 22 November 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
(1)Where an undertaker’s apparatus in a street is affected by major highway works, major bridge works or major transport works, the allowable costs of the measures needing to be taken in relation to the apparatus in consequence of the works, or in order to facilitate their execution, shall be borne by the highway, bridge or transport authority concerned and the undertaker in such manner as may be prescribed.
(2)The regulations may make provision as to the costs allowable for this purpose.
Provision may, in particular, be made for disallowing costs of the undertaker—
(a)where the apparatus in question was placed in the street after the authority had given the undertaker the prescribed notice of their intention to execute the works, or
(b)in respect of measures taken to remedy matters for which the authority were not to blame,
and for allowing only such costs of either party as are not recoverable from a third party.
(3)Where the authority have a right to recover from a third party their costs in taking measures in relation to undertaker’s apparatus but in accordance with section 84 it is determined that the measures should be taken by the undertaker, the right of the authority includes a right to recover the undertaker’s costs in taking those measures and they shall account to the undertaker for any sum received.
(4)The regulations shall provide for the allowable costs to be borne by the authority and the undertaker in such proportions as may be prescribed.
Different proportions may be prescribed for different cases or classes of case.
(5)The regulations may require the undertaker to give credit for any financial benefit to him from the betterment or deferment of renewal of the apparatus resulting from the measures taken.
(6)The regulations may make provision as to the time and manner of making any payment required under this section.
Modifications etc. (not altering text)
C1Pt. 3 modified (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), arts. 1, 3(1)
C2Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)
C3Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
C4Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))
C5Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)
C6Pt. 3 modified (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), arts. 1, 3(1)(2) (with art. 43)
C7Pt. 3 modified (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), arts. 1, 3
C8Pt. 3 modified (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), arts. 1, 4(1) (with art. 36(3))
C9Pt. 3 modified (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 4(1)(2) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)
C10Pt. 3 modified (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), arts. 1, 3(1)(2)
C11Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)
C12Pt. 3 modified (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), arts. 1, 4(1)
C13Pt. 3 modified (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), arts. 1, 4(1) (with art. 42(2))
C14Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)
C15Pt. 3 modified (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), arts. 1, 3(1)
C16Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)
C17Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)
C18Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)
C19Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)
C20Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)
C21Pt. 3 modified (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), arts. 1, 4(1) (with art. 36(2))
C22Pt. 3 modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(1)(2)
C23Pt. 3 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(1)(2) (with arts. 46, 47, Sch. 8 para. 2(7), Sch. 9 para. 4, Sch. 10 para. 12(2))
C24Pt. 3 modified (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(2)
C25Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)
C26Pt. 3 modified (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), arts. 1, 4(1) (with art. 31(2))
C27Pt. 3 modified (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 9(1)(2)(8) (with arts. 55, 56)
C28Pt. 3 applied (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(1)(2) (with art. 3(1))
C29Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)
C30Pt. 3 modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(1)(2) (with art. 32, Sch. 9 para. 36)
C31Pt. 3 modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(1)(2) (with art. 5, Sch. 27 para. 36)
C32Pt. 3 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 32 para. 1(3) (with Sch. 32 para. 1(1))
C33Pt. 3 modified (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 4 paras. 10(1), 14(3) (with Sch. 4 para. 10(2))
C34Pt. 3 modified (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(1)(2) (with arts. 6, 34)
C35Pt. 3 modified (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(1) (with arts. 62, 76, 87)
Pt. 3 modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(1)(2) (with arts. 4, 53)
C36Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)
C37Pt. 3 modified (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 11(1)(2) (with arts. 4, 52, Sch. 9 para. 82)
C38Pt. 3 modified (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(1)(2) (with art. 5)
C39Pt. 3 modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(1)(2) (with art. 4)
C40Pt. 3 modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(1)(2) (with arts. 4, 50)
C41S. 85 excluded (27.11.1992) by S.I. 1992/2984, art. 10
C42S. 85 applied (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 Pt. 4 para. 4(8)(a)
S. 85 applied (10.2.1997) by S.I. 1997/264, art. 28, Sch. 9 para. 2(7)(a)
S. 85 applied (9.11.2001) by S.I. 2001/3682, art. 33 Sch. 9 para. 2(7)(a)
S. 85 applied (9.11.2001) by S.I. 2001/3682, art. 34, Sch. 10 para. 9(5)(a) (with Sch. 10 para. 12)
C43S. 85 applied (2.4.2004) by The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004 (S.I. 2004/757), art. 1, Sch. 12 para. 2(8)(a)
C44S. 85 applied (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), Sch. 10 para. 2(7)(a) (with art. 51)
C45S. 85 applied (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), art. 1, Sch. 11 para. 7(a) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
C46S. 85 applied (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), art. 1, Sch. 9 para. 2(8) (with arts. 3(5), 15(3))
C47S. 85 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), art. 1, Sch. 10 para. 2(8) (with art. 52)
C48S. 85 applied (14.9.2006) by The Borough of Poole (Poole Harbour Opening Bridges) Order 2006 (S.I. 2006/2310), art. 1, Sch. 8 para. 2(7) (with art. 40, Sch. 7 para. 12)
C49S. 85 applied (22.11.2006) by The Docklands Light Railway (Stratford International Extension) Order 2006 (S.I. 2006/2905), art. 1, Sch. 11 para. 2(8) (with art. 43)
C50S. 85 applied (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), art. 1, Sch. 10 para. 10(5)(a) (with arts. 34, 35(2), Sch. 10 para. 13)
C51S. 85 applied (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), art. 1, Sch. 9 para. 2(7) (with arts. 34, 35(2))
C52S. 85 applied (13.12.2006) by The Luton Dunstable Translink Order 2006 (S.I. 2006/3118), art. 1, Sch. 10 para. 2(7)
C53S. 85 applied (13.12.2006) by The Network Rail (Thameslink 2000) Order 2006 (S.I. 2006/3117), art. 1, Sch. 10 para. 21(8)(a) (with arts. 34, 35(2), Sch. 10 para. 26)
C54S. 85 applied (23.8.2007) by The Docklands Light Railway (Capacity Enhancement and 2012 Games Preparation) Order 2007 (S.I. 2007/2297), art. 1, Sch. 8 para. 2(8) (with arts. 3(6), 12(3))
C55S. 85 applied (14.10.2008) by The Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (S.I. 2008/2512), art. 1, Sch. 9 para. 2(7)(a) (with art. 36(3))
C56S. 85 applied (9.6.2009) by The Nottingham Express Transit System Order 2009 (S.I. 2009/1300), art. 1, Sch. 11 para. 2(8)(a) (with Sch. 13 para. 14(2), Sch. 14 para. 19)
C57S. 85 applied (18.9.2009) by The London Underground (Victoria Station Upgrade) Order 2009 (S.I. 2009/2364), art. 1, Sch. 8 para. 2(7)(a)
C58S. 85 applied (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 1, Sch. 8 para. 2(7)(a)
C59S. 85 applied (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), art. 1, Sch. 9 para. 2(7)(a) (with art. 51, Sch. 10 paras. 68, 85)
C60S. 85 applied (21.4.2011) by The Network Rail (Hitchin (Cambridge Junction)) Order 2011 (S.I. 2011/1072), art. 1, Sch. 11 para. 2(7)(a)
C61S. 85 applied (13.11.2012) by The Chiltern Railways (Bicester to Oxford Improvements) Order 2012 (S.I. 2012/2679), art. 1, Sch. 13 para. 2(7)(a) (with art. 42(2))
C62Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)
C63S. 85 applied (28.3.2013) by The Network Rail (Seaham Level Crossing) Order 2013 (S.I. 2013/533), art. 1, Sch. para. 2(7)(a)
C64Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)
C65Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)
C66Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)
C67S. 85 applied (22.8.2013) by The Leeds Railway Station (Southern Entrance) Order 2013 (S.I. 2013/1933), art. 1, Sch. 12 para. 2(7)(a)
C68S. 85 applied (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), art. 1, Sch. 9 para. 2(8)(a) (with arts. 57, 58, Sch. 11 para. 19)
C69Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)
C70Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)
C71Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)
C72Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)
C73Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)
C74Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)
C75Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)
C76Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)
C77Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)
C78Ss. 54-106 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 13(3) (with arts. 8(5), 35, 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Pt. 2 paras. 4(2)(3), 19, Pt. 4 paras. 3, 4, 16)
C79Ss. 54-106 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 10(3) (with art. 7(6), Sch. 8 para. 10)
C80S. 85 applied (21.4.2015) by The Network Rail (Ordsall Chord) Order 2015 (S.I. 2015/780), art. 1, Sch. 11 para. 7(a) (with art. 36(2))
C81Ss. 54-106 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 9(2)
C82Ss. 54-106 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 9(3) (with arts. 51, 53)
C83Ss. 54-106 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 9(3) (with art. 44)
C84Ss. 54-106 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 10(3)
C85Ss. 54-106 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 14(3) (with arts. 35, 40, 41)
C86Ss. 54-106 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 9(3)
C87Ss. 54-106 applied (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 9(3) (with art. 26)
C88S. 85 applied (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), art. 1, Sch. 10 para. 2(7)(a)
C89Ss. 54-106 applied (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(3) (with art. 39)
C90Ss. 54-106 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 11(3)
C91Ss. 54-106 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 10(3) (with arts. 35, 36)
C92Ss. 54-106 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 10(5) (with art. 35)
C93Ss. 54-106 applied (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 11(3) (with art. 43)
C94Ss. 54-106 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 11(3)
C95Ss. 54-106 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 8(3) (with arts. 39, 40, Sch. 8 para. 19)
C96Ss. 54-106 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 10(3)
C97Ss. 54-106 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(3) (with art. 31)
C98Ss. 54-106 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 10(4)
C99S. 85: functions made exercisable concurrently (8.5.2017) by The West Midlands Combined Authority (Functions and Amendment) Order 2017 (S.I. 2017/510), arts. 1(2), 9(1)(a)(2)
C100Ss. 54-106 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 10(3)
C101Ss. 54-106 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 8(3) (with arts. 5(9), 36, 37, Sch. 8 para. 34)
C102S. 85 applied (24.8.2018) by The Network Rail (Werrington Grade Separation) Order 2018 (S.I. 2018/923), art. 1, Sch. 11 para. 2(7) (with art. 31(2))
C103Ss. 54-106 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(3) (with arts. 6, 42)
C104S. 85 applied (13.3.2019) by The Port of Tilbury (Expansion) Order 2019 (S.I. 2019/359), arts. 1, 35(7)(a) (with arts. 55, 56)
C105Ss. 54-106 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 9(3)
C106Ss. 54-106 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(3)
C107Ss. 54-106 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 9(3)
C108Ss. 54-106 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 11(3) (with art. 3(1))
C109Ss. 54-106 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 10(4) (with art. 7)
C110Ss. 54-106 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 11(3) (with art. 7)
C111S. 85 excluded (25.5.2020) by The West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511), art. 1, Sch. 13 Pt. 8 para. 3(3)
C112Ss. 54-106 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(3) (with art. 37)
C113S. 85 excluded (22.7.2020) by The Norfolk Vanguard Offshore Wind Farm Order 2020 (S.I. 2020/706), art. 1, Sch. 16 para. 30(3) (with arts. 41, 42, Sch. 16 para. 66)
C114S. 85 excluded (22.7.2020) by The Norfolk Vanguard Offshore Wind Farm Order 2020 (S.I. 2020/706), art. 1, Sch. 16 para. 14(2) (with arts. 41, 42, Sch. 16 para. 66)
C115Ss. 54-106 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 9(3) (with Sch. 9 para. 144)
C116S. 85 excluded (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), art. 1, Sch. 9 para. 122(3) (with art. 32, Sch. 9 para. 36)
C117Ss. 83-85: functions made exercisable concurrently (30.1.2021) by The West Yorkshire Combined Authority (Election of Mayor and Functions) Order 2021 (S.I. 2021/112), arts. 1(2), 22(1)(a)(2)(6)
C118Ss. 54-106 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 12(3) (with art. 5, Sch. 27 para. 36)
C119S. 85 applied (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 32 para. 35(10)(a) (with Sch. 32 para. 32(1))
C120S. 85 applied (16.4.2021) by The Network Rail (Chart Leacon) Order 2021 (S.I. 2021/419), art. 1, Sch. 5 paras. 13(a), 14
C121Ss. 54-106 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 7, Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)
C122S. 85 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), art. 1, Sch. 10 para. 2(7)(a), (8) (with arts. 15, 50, Sch. 11 para. 29)
C123S. 85 excluded (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), art. 1, Sch. 17 para. 30(3) (with arts. 41, 42, Sch. 17 para. 66)
C124S. 85 excluded (1.1.2022) by The Norfolk Boreas Offshore Wind Farm Order 2021 (S.I. 2021/1414), art. 1, Sch. 17 para. 14(2) (with arts. 41, 42, Sch. 17 para. 66)
C125S. 85 restricted (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), art. 1, Sch. 16 para. 30(3) (with arts. 41, 42, Sch. 16)
C126S. 85 restricted (5.3.2022) by The Norfolk Vanguard Offshore Wind Farm Order 2022 (S.I. 2022/138), art. 1, Sch. 16 para. 14(2) (with arts. 41, 42, Sch. 16)
C127Ss. 54-106 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 11(3) (with Sch. 8 Pt. 6 para. 19)
C128S. 85 applied (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 36(7)(a)(8) (with arts. 6, 34)
C129S. 85 applied (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 37(7)(a) (with arts. 4, 50)
C130Ss. 54-106 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 14(4) (with arts. 15, 62, 76, 87)
S. 85 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 43(7) (with arts. 62, 76, 87)
C131S. 85 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 36(7)(a) (with arts. 4, 53)
C132Ss. 54-106 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 14(3) (with arts. 4, 53)
C133S. 85 applied (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 37(7)(a) (with arts. 4, 52, Sch. 9 para. 82)
C134Ss. 54-106 applied (with modifications) (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 15(3) (with arts. 4, 52, Sch. 9 para. 82)
C135S. 85 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 34(7)(a) (with art. 5)
C136Ss. 54-106 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 10(3) (with arts. 5, 11)
C137Ss. 54-106 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 11(3) (with arts. 4, 12)
C138Ss. 54-106 applied (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 9(3) (with art. 32, Sch. 10 paras. 26(2), 68)
C139Ss. 54-106 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 15(3) (with arts. 4, 50)
C140S. 85(1)(3): functions of a local authority made exercisable by, or by employees of, such person as may be authorised in that behalf by the local highway authority whose function it is (23.7.1999) by S.I. 1999/2106, art. 2, Sch. 2 para. 4(c)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Ddeddf Gyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys